Balochistan to solarise 8,000 rebuilt houses in Awaran

PSX Update • Jul 29, 2026

The Balochistan government is set to equip 8,000 reconstructed permanent houses in Awaran district with solar power systems, completing a housing project whose cost has been revised upward from Rs2.5bn to roughly Rs2.825bn, an increase of about 13%.

July 29, 2026 (MLN): The Balochistan government is set to equip 8,000 reconstructed permanent houses in Awaran district with solar power systems, completing a housing project whose cost has been revised upward from Rs2.5bn to roughly Rs2.825bn, an increase of about 13%. The housing scheme is being financed by the Saudi Fund for Development (SFD), APP reported. The construction of all 8,000 houses has already been co...